How to Calculate Brickwork Quantity and Mortar from a Building Plan

Calculate brick quantities, wet and dry mortar volumes, cement bags, sand quantities, and standard opening deductions from building drawings.

Published by Shivam Dhiman

How to Calculate Brickwork Quantity and Mortar from a Building Plan

In Indian construction, brick masonry forms the primary envelope for external 230 mm (9-inch) walls and internal 115 mm (4.5-inch) partitions. Accurate estimation of bricks, cement bags, and sand prevents site congestion, breakage losses, and shade differences between kiln batches.

Calculating masonry materials requires converting drawings into net volumes, deducting openings, determining brick counts with wastage allowances, and computing dry mortar quantities. This article presents the step-by-step method, a worked example, common mistakes, and three practical questions.

Step-by-Step Method

Step 1: Confirm Brick Dimensions

Identify the brick standard specified in drawings:

  • Standard Modular Bricks: Dimensions are 190 mm × 90 mm × 90 mm (0.19 m × 0.09 m × 0.09 m) per IS 1077 and IS 2212. With a standard 10 mm mortar joint on all contact faces, nominal modular unit size is 200 mm × 100 mm × 100 mm (0.2 m × 0.1 m × 0.1 m).
  • Traditional Field Bricks: Common dimensions from regional kilns are 225 mm × 112 mm × 75 mm (9" × 4.5" × 3") or 225 mm × 110 mm × 75 mm.

Step 2: Calculate Gross Wall Volume

Measure wall length and clear height between floor levels or beam soffits:

Gross Wall Volume = Length × Height × Thickness

Thickness options:

  • Half-brick wall: 115 mm (0.115 m) for internal room partitions.
  • Full-brick wall: 230 mm (0.23 m) for external load-bearing or infill walls.
  • 1.5 brick wall: 345 mm (0.345 m) for foundations.

Step 3: Deduct Openings and Embedments

Apply measurement rules under IS 1200 Part 3:

  • Openings up to 0.1 m²: No deduction is made for beam ends or small pipes.
  • Openings between 0.1 m² and 0.5 m²: Deduct opening volume; make no additions for reveals or sills.
  • Openings exceeding 0.5 m²: Deduct 100% of opening volume (Width × Height × Thickness). Add actual masonry measured for reveals, sills, and jambs.
  • Structural Elements: Fully deduct RCC lintels, bed blocks, and column bands from masonry measurement.

Step 4: Determine Net Brickwork Volume

Net Brickwork Volume = Gross Wall Volume − Total Deductions

Step 5: Derive the Number of Bricks

Calculate brick quantities from nominal modular unit volume:

  • Nominal unit volume = 0.20 m × 0.10 m × 0.10 m = 0.002 m³.
  • Theoretical brick count in 1 m³ = 1 ÷ 0.002 = 500 bricks.
  • Solid volume of 500 actual bricks = 500 × (0.19 m × 0.09 m × 0.09 m) = 500 × 0.001539 m³ = 0.7695 m³.
  • Add 5% allowance for handling and cutting wastage:

Total Bricks to Order = Net Volume × 500 × 1.05 = Net Volume × 525 bricks

Step 6: Compute Wet Mortar Volume

Mortar occupies joint spaces between brick units:

  • Theoretical wet mortar volume in 1 m³ = 1.0 m³ − 0.7695 m³ = 0.2305 m³ per m³ of brickwork (approximately 23% of masonry volume).
  • In field conditions, frog filling and joint variations increase practical wet mortar consumption to 0.25 to 0.30 m³ per m³.

Step 7: Convert Wet Mortar to Dry Mortar Volume

Dry sand and cement contract when mixed with water as cement particles fill voids between sand grains:

  • Multiply wet mortar volume by dry conversion factor 1.30 to 1.33:

Dry Mortar Volume = Wet Mortar Volume × 1.33

Step 8: Calculate Cement Bags and Sand Quantities

Divide dry mortar volume by the specified mix ratio (Cement Parts : Sand Parts):

Sum of Parts = Cement Parts + Sand Parts

  • Cement Bags (50 kg): ((Cement Parts ÷ Sum of Parts) × Dry Mortar Volume × 1440 kg/m³) ÷ 50 kg (or divided by 0.0347 m³).
  • Sand Volume: (Sand Parts ÷ Sum of Parts) × Dry Mortar Volume; multiply by 35.3147 for cubic feet.

Material allocations per m³ (for 0.25 m³ wet mortar and 1.33 dry factor):

  • 1:3 Mortar: 2.45 bags cement, 0.26 m³ (9.1 cu.ft) sand. Used for water tanks.
  • 1:4 Mortar: 1.92 bags cement, 0.27 m³ (9.5 cu.ft) sand. Used for 115 mm walls.
  • 1:5 Mortar: 1.58 bags cement, 0.28 m³ (9.8 cu.ft) sand. Used for boundary walls.
  • 1:6 Mortar: 1.37 bags cement, 0.29 m³ (10.1 cu.ft) sand. Used for 230 mm walls.

Worked Example

Estimate material requirements for a bedroom wall using CM 1:6 mortar:

Wall Specifications:

  • Dimensions: Length = 5.0 m, Height = 3.0 m, Thickness = 0.23 m (230 mm).
  • Door Opening: 1.0 m × 2.1 m.
  • Window Opening: 1.5 m × 1.2 m.
  • Door Lintel: 1.3 m × 0.23 m × 0.15 m.
  • Window Lintel: 1.8 m × 0.23 m × 0.15 m.
  • Mix Ratio: 1:6 cement-sand.
  • Brick Rate: ₹9 per brick.

1. Gross Wall Volume:
5.0 × 3.0 × 0.23 = 3.450 m³

2. Deductions:
Door opening = 1.0 × 2.1 × 0.23 = 0.483 m³
Window opening = 1.5 × 1.2 × 0.23 = 0.414 m³
Door lintel = 1.3 × 0.23 × 0.15 = 0.045 m³
Window lintel = 1.8 × 0.23 × 0.15 = 0.062 m³
Total Deductions = 0.483 + 0.414 + 0.045 + 0.062 = 1.004 m³

3. Net Brickwork Volume:
3.450 − 1.004 = 2.446 m³

4. Material Requirements:
Bricks = 2.446 × 500 = 1,223 bricks. With 5% wastage: 1,223 × 1.05 = 1,284 bricks.
Total Brick Cost: 1,284 × ₹9 = ₹11,556.
Cement bags = 2.446 × 1.37 bags = 3.35 bags. Adding 3% site wastage: 3.35 × 1.03 = 3.45 bags (order 4 bags).
Sand volume = 2.446 × 10.06 cu.ft = 24.6 cu.ft. Adding 5% site wastage: 24.6 × 1.05 = 25.8 cu.ft.

Common Mistakes

  1. Laying Unsoaked Clay Bricks: Dry clay bricks absorb water from fresh mortar through capillary action, starving cement of hydration water and producing weak joints. Bricks must be immersed in clean water for at least 2 hours before laying.
  2. Inverted Frog Orientation: Laying bricks with frog downward prevents mechanical interlock. The indentation must face upward so mortar forms a shear key between courses.
  3. Overly Thick Mortar Joints: Joints must remain between 10 mm and 12 mm. Joints exceeding 15 mm reduce compressive strength by up to 25%.
  4. Ignoring Opening Deductions: Calculating materials from gross dimensions without subtracting doors, windows, and lintels inflates orders.
  5. Using Expired Mortar: Cement mortar must be placed within 60 to 90 minutes of water addition. Re-tempering stiffened mortar destroys hydration bonds.
  6. Omitting Ties in 115 mm Walls: Half-brick walls lack header bonding across thickness. Omitting two 6 mm or 8 mm steel bars in mortar beds every 3rd or 4th course causes lateral instability.

Frequently Asked Questions

How many standard modular bricks are required for 1 cubic metre of masonry?

Standard modular bricks (190 mm × 90 mm × 90 mm) with 10 mm mortar joints require 500 bricks per cubic metre theoretically (1 ÷ 0.002). Factoring in 5% cutting and handling wastage yields an order quantity of 525 bricks per cubic metre.

What mortar mix ratio is recommended for 230 mm and 115 mm brick walls?

For 230 mm (9-inch) external walls, CM 1:6 is standard per IS 2212. For 115 mm (4.5-inch) internal partition walls, a richer CM 1:4 mix is specified to provide higher tensile bond strength against lateral deflection.

Why is wet mortar volume multiplied by 1.33 to calculate dry material requirements?

Dry sand and cement contract in volume when mixed with water because fine cement grains fill void spaces between sand particles. Multiplying wet mortar volume by 1.33 compensates for this 30% to 33% shrinkage, allowing accurate batching of dry ingredients.

BTTOTEK TOOLS

Related calculators

Useful calculators related to this article.

View all calculators

BTTOTEK ANDROID APP

How to Calculate Brickwork Quantity and Mortar from a Building Plan — BTTOTEK Android App

Use the BTTOTEK Android app for this topic and many other construction, engineering, estimation and calculation tools in one place.

One app with multiple BTTOTEK calculation tools for construction, engineering, estimation, property and finance workflows.

Open on Google Play

Important information

This article is provided for general educational and calculation guidance. Information, rates, rules, standards and project requirements can change or vary by location and date. Before making an important construction, structural, property, tax, legal or financial decision, verify the relevant information with current authoritative sources, project documents or a suitably qualified professional.

KEEP READING

Related articles

Related BTTOTEK resources

Continue exploring BTTOTEK calculators, guides and useful resources.

WhatsApp

Comments

Ask a question or share your experience.

Comments are reviewed before publishing.
Loading comments...